Operations 2007
-2008 |
|
| CIMAP
Brvnik

click to download PDF
map |
|
|
|
|
|
|
   |
| |
|
   |
|
click on photos to enlarge |
|
|
Community Integration
Mine Action Plan: |
Brvnik |
|
Administrative region: |
Republika Srpska |
|
Municipality: |
Šamac |
|
Project status: |
ongoing |
|
|
|
|
Total size without
marked area: |
617.886 sqm |
|
Number of projects: |
7 |
|
Technical surveyed: |
460.750 sqm |
|
Cleared: |
5.600 sqm |
|
Permanent marking
signes: |
0 pcs |
|
Marked area: |
0 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
91 AP, 0 AT, 31 ERW |
|
Started: |
24.03.2008. |
|
Finished: |
|
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
CIMAP Boderiste

click to download PDF
map |
|
|
|
|
|
|
  |
| |
|
   |
|
click on photos to enlarge |
|
|
Community Integration
Mine Action Plan: |
Boderiste |
|
Administrative region: |
District Brčko |
|
Municipality: |
Brčko |
|
Project status: |
ongoing |
|
|
|
|
Total size without
marked area: |
567.339 sqm |
|
Number of projects: |
12 |
|
Technical surveyed: |
479.395 sqm |
|
Cleared: |
68.418 sqm |
|
Permanent marking
signes: |
36 pcs |
|
Marked area: |
122.600 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
58 AP, 6 AT, 24 ERW |
|
Started: |
06.02.2008. |
|
Finished: |
|
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
 |
|
|
|
Community Bukovac-Kladje tasks
click to
download PDF map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Bukovac - Kladje |
|
Administrative region: |
Distrikt Brčko |
|
Project status: |
completed |
|
|
|
|
Total size without
marked area: |
339.166 sqm |
|
Number of projects: |
7 |
|
Technical surveyed: |
274.651 sqm |
|
Cleared: |
64.515sqm |
|
Permanent marking
signes: |
89 pcs |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
22 AP, 2 AT, 11 ERW |
|
Started: |
23.11.2006. |
|
Finished: |
20.05.2008. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
 |
|
|
|
|
Community Obudovac tasks

click to download PDF
map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Obudovac |
|
Administrative region: |
Republika Srpska |
|
Municipality: |
Šamac |
|
Project status: |
completed |
|
|
|
|
Total size: |
189.960 sqm |
|
Number of projects: |
4 |
|
Technical surveyed: |
130.910 sqm |
|
Cleared: |
59.050 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD |
|
Founded mines/ERW:
|
10 AP, 14 ERW |
|
Started: |
05.11.2007. |
|
Finished: |
03.03.2008. |
|
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
 |
|
|
|
|
Community Ladjevici tasks

click to download PDF
map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Lađevići |
|
Administrative region: |
Sarajevski kanton |
|
Municipality: |
Ilijaš |
|
Project status: |
ongoing |
|
|
|
|
Total size without
marked area: |
69.540 sqm |
|
Number of projects: |
2 |
|
Technical surveyed: |
42.921 sqm |
|
Cleared: |
26.619 sqm |
|
Permanent marking
signes: |
5 pcs |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
36 AP, 2 AT, 47 ERW |
|
Started: |
03.05.2007. |
|
Finished: |
30.06.2008. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
Community Širokača task

click to download PDF
map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Širokača |
|
Administrative region: |
Sarajevski kanton |
|
Municipality: |
Stari grad |
|
Project status: |
ongoing |
|
|
|
|
Total size without
marked area: |
36.306 sqm |
|
Number of projects: |
1 |
|
Technical surveyed: |
0 sqm |
|
Cleared: |
17.749 sqm |
|
Permanent marking
signes: |
5 pcs |
|
Demining methods: |
manual demining |
|
Founded mines/ERW:
|
74 AP, 1 AT, 19 ERW |
|
Started: |
5.09.2006. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
Community Grivići tasks

click to
download PDF map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Grivići |
|
Administrative region: |
Sarajevski kanton |
|
Municipality: |
Hadžići |
|
Project status: |
completed |
|
|
|
|
Total size: |
12.783 sqm |
|
Number of projects: |
1 |
|
Technical surveyed: |
12.783 sqm |
|
Demining methods: |
manual demining |
|
Founded mines/ERW: |
0 AP, 0 AT, 0 ERW |
|
Started: |
05.11.2007. |
|
Finished: |
22.05.2008. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
CIMAP Donje Dubravice

click to download PDF
map |
|
|
|
Community Integration
Mine Action Plan: |
Donje Dubravice |
|
Administrative region: |
Distrikt Brčko |
|
Project status: |
completed |
|
|
|
|
Total size without
marked area: |
280.138 sqm |
|
Number of projects: |
12 |
|
Technical surveyed: |
249.127 sqm |
|
Cleared: |
31.012 sqm |
|
Permanent marking
signes: |
77 pcs |
|
Marked area: |
1.137.887 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD |
|
Founded mines/ERW:
|
16 AP, 6 AT, 6 ERW |
|
Started: |
07.03.2007. |
|
Finished: |
03.10.2007. |
|
|
|
Mine risk education and
Community liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
| CIMAP Vidovice
 
click to download PDF
map |
|
|
|
Community Integration
Mine Action Plan: |
Vidovice |
|
Administrative region: |
Posavski kanton |
|
Municipality: |
Orašje |
|
Project status: |
completed |
|
|
|
|
Total size without
marked area: |
412.062 sqm |
|
Number of projects: |
7 |
|
Technical surveyed: |
408.455 sqm |
|
Cleared: |
3.607 sqm |
|
Permanent marking
signes: |
12 pcs |
|
Marked area: |
89.630 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
22 AP, 1 AT, 25 ERW |
|
Started: |
12.03.2007. |
|
Finished: |
15.10.2007. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
Community
Dubrave tasks

click to download PDF
map |
|
|
|
Community: |
Dubrave |
|
Administrative region: |
Distrikt Brčko |
|
Project status: |
completed |
|
|
|
|
Total size: |
268.228 sqm |
|
Number of projects: |
3 |
|
Technical surveyed: |
233.370 sqm |
|
Cleared: |
34.858 sqm |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD |
|
Founded mines/ERW:
|
17 AP, 6 ERW |
|
Started: |
25.04.2007. |
|
Finished: |
27.11.2007. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
Community Salkanov han tasks

click to download PDF
map |
|
| |
|
before operations |
| |
|
operations |
|
|
Community: |
Salkanov Han |
|
Administrative region: |
Sarajevski Canton |
|
Municipality: |
Ilijaš |
|
Project status: |
completed |
|
|
|
|
Total size without
marked area: |
61.591 sqm |
|
Number of projects: |
2 |
|
Technical surveyed: |
58.362 sqm |
|
Cleared: |
3.329 sqm |
|
Permanent marking
signes: |
2 pcs |
|
Demining methods: |
mechanical preparation of ground, manual
demining, MDD
|
|
Founded mines/ERW:
|
2 AP, 0 AT, 1 ERW |
|
Started: |
05.03.2007. |
|
Finished: |
25.05.2007. |
|
|
|
Mine risk education and Community
liasion activities have been conducted continuously during project
implementation. |
|
|
|
Supported by: |
|
|
|
|
  |
|
|
|
|
CIMAP Avramovina |